2025-10-24
Seal - HV Input Header (Model YL) (Remove and Replace)
Correction code
16300501202
FRT
1.32
NOTE: Unless otherwise explicitly stated in the procedure, the correction code and FRT listed above reflect all of the work required to perform this procedure, including the linked procedures. Do not stack correction codes unless explicitly told to do so.
NOTE: See Flat Rate Times to learn more about FRTs and how they are created.
NOTE: See Personal Protection to make sure you
are wearing proper PPE when performing the procedure below.
NOTE: See Ergonomic Precautions for safe and healthy working practices.
Torque Specifications
| Description | Torque Value | Recommended Tools | Reuse/Replace | Notes |
|---|---|---|---|---|
| Bolt securing the busbar cover access door |
![]() 9 Nm (6.6 lbs-ft) |
|
Reuse | |
| Bolts (x2) that attach the charge port busbar kit to the HV header |
![]() 9 Nm (6.6 lbs-ft) |
|
Reuse | |
| Bolts (x4) that attach the input header seal to the ancillary bay |
![]() 10 Nm (7.4 lbs-ft) |
|
Reuse |
Remove
- Raise and support the vehicle. See Raise Vehicle - 2-Post Lift.
- Remove the 2nd row LH and RH seats. See Seat Assembly - 2nd Row - LH (Model YL) (Remove and Replace).
- Remove the 3rd row LH and RH seat cushion bolsters. See Bolster - Seat Cushion - 3rd Row - LH (Model YL) (Remove and Replace) and Bolster - Seat Cushion - 3rd Row - RH (Model YL) (Remove and Replace).
- Remove the LH and RH lower C-pillar trims. See Trim - C-Pillar - Lower - LH (Model YL) (Remove and Replace).
-
Remove the clips (x2) that attach the
rear cabin carpet harness to the body.
-
Release the datums (x2), then fold the
rear cabin carpet to access the rear inner HV battery ancillary bay.
CAUTIONPull the carpet out from both side trunk trims, and ensure the 2nd row seat harness is threaded through the carpet.
- Perform the vehicle HV disablement procedure. See Vehicle HV Disablement Procedure (Model YL) (Maintenance).
- Put on HV insulating gloves and leather over gloves.
-
Remove the bolt securing the busbar
cover access door.
TIpUse of the following tool(s) is recommended:
- SKT, 1/4" SQ DR, 10MM, UNIV, HV INSULATED
-
Remove the bolts (x2) that attach the
charge port busbar kit to the HV header.
TIpUse of the following tool(s) is recommended:
- SKT, 1/4" SQ DR, 10MM, UNIV, HV INSULATED
-
Use an inflatable air bag to lift the
busbar kit connector away from the HV header.
NoteDuring the process, note the following:
- Hold the busbar firmly as there is tension on.
- Avoid damaging the harness bracket.
-
Remove the bolts (x4) that attach the
input header seal to the ancillary bay.
TIpUse of the following tool(s) is recommended:
- Penthouse Socket, 1/4" Dr, 5-Lobe, E-Torx Mag
-
Release the location pins (x2) to
remove the input header seal from the ancillary bay.
Replace
-
Align the location pins (x2) and
install the input header seal to the ancillary bay.
NoteCheck the sealing ring for damage, and replace the input header seal if necessary.
-
Install the bolts (x4) that attach the
input header seal to the ancillary bay.
10 Nm (7.4 lbs-ft)TIpUse of the following tool(s) is recommended:- Penthouse Socket, 1/4" Dr, 5-Lobe, E-Torx Mag
NoteMark the bolts after torque. -
Use IPA wipes to clean the HV
connector contact surface and the busbar HV connector contact surface of the residual
Penetrox. Allow one minute of drying time for each surface.
NoteA new busbar comes with Penetrox pre-applied to the HV connector; clean the contact surface of the busbar HV connector when reusing a busbar.
-
Apply Penetrox onto the HV connector joints. Apply 2 drops of Penetrox A-13 (about
5mm in diameter) on each side of the hole on both leads, and spread evenly to ensure
full coverage of the contact surface.
-
Remove the inflatable air bag from
under the HV header.
-
Position the busbar kit connector, lower it onto the HV header while lifting the rear
end of the busbar assembly to ease installation.
NoteInspect for damage and replace if excessive force is needed to seat the busbar.
-
Install the bolts (x2) that attach the
charge port busbar kit to the HV header.
9 Nm (6.6 lbs-ft)TIpUse of the following tool(s) is recommended:- SKT, 1/4" SQ DR, 10MM, UNIV, HV INSULATED
NoteMark the bolts after torque. -
Perform Hioki resistance test at each of the 2 HV joints from HV busbar lead to bolt
head; acceptable resistance is 0.050 mΩ (50 μΩ) to 0.195 mΩ (195 μΩ).
- If above 0.195 mΩ, stop work and escalate to Toolbox session;
- If below 0.050 mΩ, reposition probes and remeasure;
- If repeatedly between 0.00 mΩ and 0.050 mΩ, test passed, proceed to next step.
-
Install the bolt securing the busbar
cover access door.
9 Nm (6.6 lbs-ft)TIpUse of the following tool(s) is recommended:- SKT, 1/4" SQ DR, 10MM, UNIV, HV INSULATED
-
Align the datums (x2), then fold the
rear cabin carpet to its original position.
CAUTIONInsert the carpet under the trunk side trim on both sides, and ensure the 2nd row seat harness is threaded through the carpet.
- Install the LH and RH lower C-pillar trims. See Trim - C-Pillar - Lower - LH (Model YL) (Remove and Replace).
-
Install the clips (x2) that attach the
rear cabin carpet harness to the body.
- Install the 3rd row LH and RH seat cushion bolsters. See Bolster - Seat Cushion - 3rd Row - LH (Model YL) (Remove and Replace) and Bolster - Seat Cushion - 3rd Row - RH (Model YL) (Remove and Replace).
- Install the 2nd row LH and RH seats. See Seat Assembly - 2nd Row - LH (Model YL) (Remove and Replace).
- Remove the vehicle from the lift.