HV Battery Air Leak Test (Standard) (Test/Adjust)
Correction code
16102200
1.44
NOTE: Unless
otherwise explicitly stated in the procedure, the correction code and its
associated FRT reflect all of the work required to perform this procedure,
including the linked procedures. Do not stack correction
codes unless explicitly told to do so.
NOTE: See Flat Rate Times to
learn more about FRTs and how they are created.
NOTE: See Personal Protection to make
sure you are wearing proper PPE when performing the procedure below.
NOTE: See Ergonomic Precautions for safe and healthy
working practices.
High Voltage Awareness Care Pointsfor additional glove and safety information.
- 2026-05-08: Released new procedure.
- Raise and support the vehicle. See Raise Vehicle - 2 Post Lift.
- Open the LH front door and lower the LH front window.
- Open the tonneau cover.
- Open the tailgate.
- Remove the bed floor assembly. See Bed Floor Assembly (Remove and Install).
- Remove the NVH barrier. See Tonneau NVH Barrier Assembly (Standard) (Remove and Install).
- Disconnect MV power. See Mid-Voltage Power (Disconnect and Connect) (Modify).
- Perform Vehicle HV Disablement procedure. See Vehicle HV Disablement Procedure (without Terrestrial Armor) (Test/Adjust).
-
Inspect thermal vent breather
plugs
Note4x plugs, If plug has laser etchings in line then replace, If plug is loose then press to get audible click
-
Inspect pyro access cover breather
plug
Note1x plug, If plug has laser etchings in line then replace, If plug is loose then press to get audible click
-
Loosen bolts securing 2x4 header
assembly to enclosure
Note4x bolts, 5-lobe E10, 6 Nm, Use hand tools only, Adjust assembly as needed, Do not remove connectors unless soft set is found
-
Torque bolts securing 2x4 header
assembly to enclosure
Note4x bolts, 5-lobe E10, 6 Nm, Use hand tools only, Adjust assembly as needed, Do not remove connectors unless soft set is found
-
Remove breather plug from thermal
vent
Note1x plug, 3x tabs per plug, Discard after removal
-
Apply butyl onto remaining thermal
vents
Note3x butyl patches, 3x thermal vents
-
Install enclosure leak test adapter onto
open thermal vent
Note1x thermal vent
-
Connect enclosure leak tester onto
adapter
Note1x adapter
-
Close both valves on regulator
-
Connect regulator to air supply
-
Turn right side regulator valve to open
position
NoteTurn valve knob to horizontal position
-
Set regulator to 0.3 psi
-
Open left side regulator valve to inject
air into platter
NoteClose right side regulator valve when pressure reaches 0.3 psi and stabilizes, Allow platter to fill for 120 seconds
- Wait 30 seconds for pressure to settle
- Record value of starting pressure
- Wait 30 seconds to test pressure
-
Record value of end pressure
NoteSubtract ending pressure from starting pressure, If difference is greater than 0.006 psi then inspect tools and retest, If difference is still greater than 0.006 psi then escalate to Service Engineering, If difference is 0.006 psi or less then proceed with current procedure
-
Remove enclosure leak test adapter from
open thermal vent
Note1x thermal vent
-
Remove butyl from remaining thermal
vents
Note3x butyl patches, 3x thermal vents
-
Install breather plug onto thermal
vent
Note1x plug, 3x tabs per plug, Install new plug, Press plug evenly, Make sure tabs are fully engaged and plug is flush with vent
-
Remove breather plug from pyro access
cover
Note1x plug, 3x tabs per plug, Discard after removal
-
Install enclosure leak test adapter onto
pyro access cover breather hole
Note1x thermal vent
-
Close both valves on regulator
-
Turn right side regulator valve to open
position
NoteTurn valve knob to horizontal position
-
Set regulator to 0.3 psi
-
Open left side regulator valve to inject
air into ancillary bay
NoteClose right side regulator valve when pressure reaches 0.3 psi and stabilizes, Allow bay to fill for 120 seconds
- Wait 30 seconds for pressure to settle
- Record value of starting pressure
- Wait 30 seconds to test pressure
-
Record value of end pressure
NoteSubtract ending pressure from starting pressure, If difference is greater than 0.05 psi then inspect tools and retest, If difference is still greater than 0.05 psi then escalate to Service Engineering, If difference is 0.05 psi or less then proceed with current procedure
-
Close both valves on regulator
-
Turn right side regulator valve to open
position
NoteTurn valve knob to horizontal position
-
Set regulator to 0.8 psi
-
Open left side regulator valve to inject
air into ancillary bay
NoteClose right side regulator valve when pressure reaches 0.8 psi and stabilizes, Allow bay to fill for 120 seconds
-
Inspect 2x4 header assembly for air
leak
Note2x headers, Spray with soapy water as needed, Do not disconnect connectors, If leak found then proceed to replacement procedure
-
Inspect pyro access cover for air
leak
NoteSpray with soapy water as needed, If leak found then proceed to replacement procedure
-
Inspect PCS coolant passthrough for air
leak
Note2x hoses, Spray with soapy water as needed, Do not disconnect hoses, If leak found then proceed to replacement procedure
-
Inspect DU HV headers for air leak
Note3x headers, Spray with soapy water as needed, Do not disconnect connectors, If leak found then proceed to replacement procedure
-
Inspect ancillary bay flood ports for
air leak
Note3x ports, Spray with soapy water as needed, If leak found then proceed to replacement procedure
-
Lower vehicle until tires are touching
the ground
NoteRaise lift off locks, then hold lock release lever to keep locks free while vehicle is lowered
-
Remove bolt securing busbar HV connector
lid
Note1x bolt, EP10, 9 Nm
-
Remove bolts securing HV connector to DC
FC header
Note2x bolts, 10mm, 9 Nm
-
Release HV connector from DC FC
header
Note1x connector, Use inflatable airbag if needed to suspend busbar assembly above ancillary assembly
-
Install CP busbar dummy plug onto DC FC
header
Note1x bolt, 10mm, 9 Nm, Shift plug up and down a few times to work grease onto seal grooves
-
Raise vehicle fully
NoteSet to a comfortable working height, Lower to locks, Ensure locks engage on both sides to prevent tilting
-
Close both valves on regulator
-
Turn right side regulator valve to open
position
NoteTurn valve knob to horizontal position
-
Set regulator to 0.3 psi
-
Open left side regulator valve to inject
air into ancillary bay
NoteClose right side regulator valve when pressure reaches 0.3 psi and stabilizes, Allow bay to fill for 120 seconds
- Wait 30 seconds for pressure to settle
- Record value of starting pressure
- Wait 30 seconds to test pressure
-
Record value of end pressure
NoteSubtract ending pressure from starting pressure, If difference is greater than 0.05 psi then inspect tools and retest, If difference is still greater than 0.05 psi then escalate to Service Engineering, If difference is 0.05 psi or less then proceed to repair procedure
-
Disconnect air supply from
regulator
-
Disconnect enclosure leak tester from
adapter
Note1x adapter
-
Remove enclosure leak test adapter from
pyro access cover breather hole
Note1x thermal vent
-
Install rear skid plate
Note6x clips, 3x bolts, 15mm, 42 Nm, 5x bolts, 13mm, 28 Nm, 2x bolts, 10mm, 6 Nm, Apply Loctite 222 to mid aero shield bolts and install fasteners
-
Lower vehicle fully
NoteRaise lift off locks, then hold lock release lever to keep locks free while vehicle is lowered
-
Remove CP busbar dummy plug from DC FC
header
Note1x bolt, 10mm, 9 Nm
-
Position busbar connector and lower onto
HV header
NoteRelease bungee cord
-
Install bolts securing charge port
busbar kit to HV Header
Note2x bolts, 10mm, 9 Nm
-
Perform Hioki resistance test at each HV
joint from HV busbar lead to bolt head
Note2x HV joints, When using Hioki tester, verify the meter has been properly adjusted and set prior to usageThe acceptable resistance is between 0.050 mΩ (50 μΩ) and 0.195 mΩ (195 μΩ).If the resistance is greater than 0.195 mΩ (195 μΩ), stop work and escalate the Toolbox session.If the resistance is lower than 0.050 mΩ (50 μΩ), reposition the probes and measure again.If the resistance is repeatedly between 0.00 mΩ and 0.050 mΩ (50 μΩ), hioki test passed, proceed to next step
-
Install bolt securing busbar HV
connector lid
Note1x bolt, EP10, 9 Nm
- Remove leather over gloves and HV insulating gloves
- Install the tonneau NVH barrier assembly. See Tonneau NVH Barrier Assembly (Standard) (Remove and Install).
- Install the bed floor assembly. See Bed Floor Assembly (Remove and Install).
- Reconnect MV power. See Mid-Voltage Power (Disconnect and Connect) (Modify).
- Close the tonneau cover.
- Close the tailgate.
- Remove the vehicle from the lift. See Raise Vehicle - 2 Post Lift.
- Raise the LH front window and close the LH front door.